ON going projects
Amplia Infrastructures is currently working on the expansion of over 130 km of carriageway on the A/9 (Lainate Como - Chiasso), on the A/14 (the North Rimini Cattolica; Fano Senigallia and North Rimini - Pedaso sections) and on the A/1 (Barberino di Mugello - Incisa Valdarno and North Florence- South Florence sections). Works are also underway to build or replace safety and noise barriers along numerous sections of the motorway network. Pavimental is also starting work on the construction of interchanges Genova San Benigno, Crespellano and industrial area of Foggia and those related to Rho-Monza. The total amount of the works exceeds EUR 1,350 million. Read More
Bosco Grande Viaduct
Refurbishment of the safety barriers on the outside of the Bosco Grande Viaduct at km 52+733, located on the A16 Naples-Canosa highway on the East and West carriageways, for which the 6th Stretch head office of Autostrade per l’Italia S.p.A. is…

Via della Superba - Genoa
Road reserved for heavy vehicles heading to the port of Genoa opened on 19 September 2018 Length: 3.7 km Duration of the work: 27 consecutive days (22 August to 18 September 2018) Workforce used: 50 resources Quantity of bituminous…

Highway A4 Turin-Venice Expansion to four…
Highway A4 Turin-Venice – Expansion to four lanes of the highway stretch between the exit for Viale Certosa and the exit for Sesto San Giovanni Project value: € 116 million Start of works: 16 January 2016 Main…

Lot 2 - Santa Lucia Tunnel A1 - Expansion to…
The project for the Barberino di Mugello – Incisa Valdarno expansion to three lanes, in the Barberino di Mugello – Florence North stretch, covers from marker 261+503 (corresponding to the Barberino di Mugello exit) and marker 279+000…

Rebuilding of the viaduct connecting the A1…
The rebuilding of the Lepido viaduct at Borgo Panigale completed in only 53 days. The works, which started the day after the collapse of a span of the overpass caused by an accident in which a tanker exploded, were initially expected to take 5…

Compensatory works Municipality of Fano
Interventions for the period March 2017 - July 2019 1- LINK ROAD SP3 - VIA CAMPANELLA The project establishes the connection between (Paved Road) SP3 Flaminia and via Tommaso Campanella, the main local road network. The link road is composed…

A1 MILAN NAPLES MOTORWAY WORKS ON APPENNINE…
Project value: Euro 31,010,798.86 Earth movements: 231,052 m3 Sub-foundations: 47,308 m3 Concrete: 13,487 m3 Asphalt road surface: 47,308 TONNES Draining pavement: 13,505…
A1 Milan Naples. Construction of the third…
The project constitutes a small part of the construction of the third lane of the A1 Milan – Naples motorway, on the stretch from Florence South to Incisa. The construction project is aimed at bringing the existing infrastructure to a…