Napoli Capodichino International Airport
Value of the project (gross): € 2,130,947.10
Expertise value (net): 1,617,678.27
Completion of work (by contract): 04/01/2014
Start of construction: 12/02/2013
End of Work: 03/14/2014
Expected duration of work: 120 days
Actual duration of work: 103 days
Earth-moving works: 300 mc
Stabilizations background: 5.000 cbm
Asphalt paving 13,200 tons
Main interventions:
milling asphalt concrete
stabilization in cement background
paving asphalt concrete (base, binder, wear)
excavation section for laying conduits medium voltage systems AVL
laying AVL systems
Contract for renewal of pavement taxiway "TS" connections between "D" and "E".