Leonardo Da Vinci Airport - Fiumicino - Structural and operational refurbishing of the flight infrastructures of Runway 16L/34R



 

Structural and operational refurbishing of the flight infrastructures of Runway 16L/34R

 

 

 

 

 

 

Project value: 87.738.917,60 Euros

 

End of works (as per contract): September 2015

 

Start of works: September 2014

End of works: September 2015

Expected duration of works: 320 days

Effective duration of works: 320 days

Earth movements: 1.028.489,10 m3

Sub-foundations: 254.826,39 m3

Concrete: 20.709,66 m3

Asphalt surfacing: 435.987,58 TONNES

Main interventions carried out: Organisation of the areas used as Runway Strip of runway 16L/34R. Structural/functional refurbishment of the surfacing of taxiway Delta between lanes “DA” and “DL”. Structural/functional refurbishment of the surfacing of the lanes between the runway and taxiway Delta (from “DA” to “DL”). Widening of the load-bearing surfacing and the anti-dust areas of taxi lanes “DA”, “DB”, “DC”, “DH”, “DK” and “DL”, in order to enable the transit of new ICAO code “F” A380 type aircraft.

Enhancement of the existing network for the collection of rainwater near runway 16L/34R.

 

Refurbishment/Re-protection of the existing AVL installations, taxiway Delta and the taxi lanes between the runway and taxiway Delta.